You work as a scheduler for your organization. You are developing a schedule and its constraints
for the SAP project. There are nine inputs to develop a project schedule. Which of the following is
NOT an input to the schedule development process?

A.
Work breakdown structure
B.
Activity attributes
C.
Resource calendars
D.
Activity list
Explanation:
The WBS is not an input, directly, to the develop schedule process. Technically, you will need the
scope baseline, which does include the WBS. The inputs in developing a schedule process are of
nine types, which are as follows:
Activity list
Activity attributes
Project schedule network diagrams
Activity resource requirements
Resource calendars
Activity duration estimates
Project scope statement
Enterprise environmental factors
Organization process assets