Which of the following is an output of the Develop Project Charter process?

Which of the following is an output of the Develop Project Charter process?

PrepAway - Latest Free Exam Questions & Answers

A.
Enterprise environmental factors

B.
Contract

C.
Business case

D.
Project charter

Explanation:
The Develop Project Charter process documents the formal authorization of a project or a phase.
It also documents initial requirements that satisfy the stakeholder’s needs and expectations. It is
used to validate the decisions made during the previous iteration of the Develop Project Charter
process. The various inputs of this process are as follows:
Project statement of work

Business case
Contract
Enterprise environmental factors
Organizational process assets
The output of the Develop project Charter process is as follows:
Project charter