Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project.
There are eight tools and techniques that a project manager can use to develop the project
schedule. Which of the following is a tool and technique for the Schedule Development process?

A.
Schedule compression
B.
Reserve analysis
C.
Variance analysis
D.
Expert judgment
Explanation:
Schedule compression is a tool used as part of the Schedule Development process. The tools and
techniques for schedule development are as follows:
Schedule network analysis
Critical path method
Critical chain method
Resource leveling
What-if scenario analysis
Applying leads and lags
Schedule compression
Scheduling tool
Answer options D, B, and C are incorrect. These are not tools and techniques for schedule
development.