Which of the following is a tool and technique for the Schedule Development process?

Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project.
There are eight tools and techniques that a project manager can use to develop the project
schedule. Which of the following is a tool and technique for the Schedule Development process?

PrepAway - Latest Free Exam Questions & Answers

A.
Schedule compression

B.
Reserve analysis

C.
Variance analysis

D.
Expert judgment

Explanation:
Schedule compression is a tool used as part of the Schedule Development process. The tools and
techniques for schedule development are as follows:
Schedule network analysis
Critical path method
Critical chain method
Resource leveling
What-if scenario analysis
Applying leads and lags
Schedule compression
Scheduling tool
Answer options D, B, and C are incorrect. These are not tools and techniques for schedule
development.