Don is the project manager of the NQP project for his organization. This project is scheduled to
last for 18 months and will have several elements of the project that have government regulations.
Management is concerned with the regulations and would like Don to report on the activities that
will be affected by the regulations. Which of the following documents should Don refer to, for the
information on the activities and the regulations?

A.
Risk management plan
B.
Activity list
C.
Activity list and attributes
D.
Risk register
Explanation:
The activity list and the attributes will contain the information about the activities that interact with
the government regulations.Answer option A is incorrect. The risk management plan communicates how the risks will be
identified, analyzed, responded to, and monitored.
Answer option D is incorrect. The risk register is a list of all the risk events for the project.
Answer option B is incorrect. The activity list is not a detailed enough answer for this question.