Where else should Robert reflect these project changes?

Vicky is the project sponsor of Robert’s project. She has requested several changes for the project
scope and these changes have, of course, been approved. Robert needs to incorporate the
project scope changes into the activity list. Where else should Robert reflect these project
changes?

PrepAway - Latest Free Exam Questions & Answers

A.
Project final report

B.
Scope baseline

C.
Quality control mechanism

D.
Cost baseline

Explanation:
All scope changes should also be updated in the project scope baseline. The scope baseline is the
project scope statement, work breakdown structure (WBS), and the WBS dictionary.
Answer option D is incorrect. If the changes affect cost then the cost baseline would also be
updated. The question did not indicate that therbe would a change in the project cost.
Answer option C is incorrect. Quality control does not change. It always reflects the demands of
the project scope.
Answer option A is incorrect. The project final report evaluates the success and failures of the
project scope.