PrepAway - Latest Free Exam Questions & Answers

What will likely happen to your project now?

You are the project manager for your organization. You have created the project schedule and
have presented it to the management for their approval. Management decides to enforce resource

leveling heuristics on your project schedule. What will likely happen to your project now?

PrepAway - Latest Free Exam Questions & Answers

A.
It will require fewer resources due to the cut in the project scope.

B.
It will require additional resources for the additions to the project scope.

C.
It will require additional resources if it is to finish in the same amount of time, as originally
predicted.

D.
It will require a new scope baseline to reflect the management change in the project approach.

Explanation:
Resource leveling heuristics limits the amount of time a resource is allowed to work in a given time
period. This action typically increases the project duration. By adding additional resources to
effort-driven activity the project can still complete, often, in the same schedule, otherwise the
duration of the project will increase.
Answer option B is incorrect. Resource leveling heuristics does not change the project scope.
Answer option A is incorrect. This is not an instance of cutting the project scope.
Answer option D is incorrect. The project scope baseline is not affected by resource leveling
heuristics.


Leave a Reply