what was expected?

You are the project manager for your company. You are working with the activities defined in the
figure below.

What will happen to your project if Activity F takes five additional days to complete than what was
expected?

PrepAway - Latest Free Exam Questions & Answers

A.
Your project’s critical path will shift to ACFI.

B.
Your project will be late by five days.

C.
Your project can still complete on time as float is available onActivity I.

D.
Your project will now have two critical paths.

Explanation:
Activity F is on the critical path of ACFHK of 30 days. By adding five additional days to Activity F,
the project will now take 35 days to complete.
Answer options C, A, and D are incorrect. These are not the valid answers.