You work as a project manager for BlueWell Inc. Some of the activities in your project are not
being completed on time. You reviewed these activities with your project team and discovered that
the time estimates for the project are much more aggressive than what they are actually
experiencing in the completion of the activities. You elect to create a new schedule for the project.
What project Management process are you working with when you create a new target schedule?

PrepAway - Latest Free Exam Questions & Answers

A.
Develop schedule

B.
Estimate activity durations

C.
Control schedule

D.
Estimate activity resources

Explanation:
In severe cases, new schedule duration estimates with new forecasted start and finish dates are
needed. In these instances, it is an example of using the control schedule process. Control

schedule process is a method of monitoring the status of the project to update project progress
and deal with the changes to the schedule baseline. It is concerned with:
Determining the current status of the project
Influencing the factors that create schedule changes
Determining that the project schedule has changed
Managing the actual changes as they occur
Control schedule is a component of the Perform Integration Change Control process.
Answer option D is incorrect. The activity resources would only address the addition or
replacement of resources needed to complete the project work.
Answer option B is incorrect. This is a tempting choice, but new schedules are a part of the control
schedule process.
Answer option A is incorrect. Develop schedule is not the best choice for this question.