What other tool Winnie can use to help and generate an updated project schedule?

Winnie is the project manager for her company. She has been recording the actual durations of
the project work to determine the actual progress of her project. Winnie needs to generate an
updated project schedule based on project performance. She is using the supporting schedule
data, manual scheduling methods, and her project management software to perform schedule
network analysis. What other tool Winnie can use to help and generate an updated project
schedule?

PrepAway - Latest Free Exam Questions & Answers

A.
Critical path method

B.
Schedule management plan

C.
Scheduling tool

D.
Critical chain method

Explanation:
Answer option A is incorrect. The critical path method can be analyzed, but it is a part of the
project management information system. In addition, the critical path is not better or worse than
the critical chain method so by having both answers among the choices both answers are
cancelled.
Answer option D is incorrect. The critical chain method can be analyzed, but it is the part of the
project management information system. In addition, the critical path is not better or worse than
the critical path method so by having both answers among the choices both answers are
cancelled.
Answer option B is incorrect. The schedule management plan may need to be referenced to
create a new project schedule, but it is not a tool that Winnie can use.