What is the term assigned to graphic in the figure given below?

What is the term assigned to graphic in the figure given below?

PrepAway - Latest Free Exam Questions & Answers

A.
Communications bull’s eye

B.
Performance goals

C.
Earned value management goals

D.
Project exception report

Explanation:
The graphic shown in the figure is a communications bull’s eye. The project manager must keep
the project within the boundaries defined by the bull’s eye or he will need to generate a
performance report. This is an example of management by exception because the project
manager only communicates with management when there is an exception, or variance, within the
project.
Answer options C, B, and D are incorrect. These are not valid terms for the communications bull’s
eye.