What is the latest day Activity I can finish without affecting the project end date?

Jeff is the project manager of the GHY Project for his organization. He has created the project
network diagram as shown in the figure:

Management is reviewing the network diagram, and they are concerned about the latest date that
Activity I can finish. What is the latest day Activity I can finish without affecting the project end
date?

PrepAway - Latest Free Exam Questions & Answers

A.
Day 20

B.
Day 22

C.
Day 17

D.
Day 19

Explanation:
Activity I must finish by Day 22, so that Activity J can start by Day 23. If Activity I finishes later than
Day 22, the project will be late.
Answer option D is incorrect. Day 19 is the earliest Activity I can finish.

Answer option A is incorrect. Day 20 is the latest Activity I can start.
Answer option C is incorrect. Day 17 is the earliest Activity I can start.