Your project is installing 8,000 light fixtures in a new building. Each of the light fixtures is to be
installed exactly the same way but you have discovered that some of the fixtures are installed
incorrectly. You and the project team meet and agree to fix the fixtures and to install all future
fixtures the same way. This is an example of what executing activity?

A.
Risk response
B.
Team development
C.
Risk mitigation
D.
Corrective action
Explanation:
This is an example of corrective action. The project team will fix the mistake and they have learned
from their mistake so it won’t happen again.
Answer option C is incorrect. Risk mitigation is defined as monies spent or actions taken to reduce
the probability and impact of an identified risk event.
Answer option A is incorrect. A risk response is an action to counteract an identified risk.Answer option B is incorrect. There may be some team development happening in this instance
but we don’t have enough information to know for certain. Team development is an activity that