PrepAway - Latest Free Exam Questions & Answers

What does this figure depict?

Della works as a Project Manager for BlueWell Inc. A number of projects are running under her
guidance. You, being a team leader of a project, provide Della the performance indexes of your
project. The schedule variance (SV) of your project is zero. What does this figure depict?

PrepAway - Latest Free Exam Questions & Answers

A.
Project is right on target.

B.
Project is ahead of the schedule.

C.
Project is behind the schedule.

D.
Costs are higher than planned.

Explanation:
According to the question, the schedule variance (SV) of the project is zero. A value of 0 indicates
that the project is right on target. Schedule variance (SV) is a measure of schedule performance
on a project. The variance notifies that the schedule is ahead or behind what was planned for this
period in time. The schedule variance is calculated based on the following formula: SV = Earned
Value (EV) – Planned Value (PV) If the resulting schedule is negative, it indicates that the project is
behind schedule. A value greater than 0 shows that the project is ahead of the planned schedule.
A value of 0 indicates that the project is right on target.
Answer option C is incorrect. The negative SV means that project is behind the schedule.
Answer option D is incorrect. This result can be drawn by looking at the cost variance (CV) of the
project.
Answer option B is incorrect. The positive SV depicts that the project is ahead of the planned
schedule.


Leave a Reply