Tom is the project manager of the HQQ Project. His project has a schedule variance of -$34,500
due to some errors early in the project. Management would like to know how Tom will respond to
these variances. What action can help Tom to manage the errors in the project and to ensure that
the errors would not occur again?

PrepAway - Latest Free Exam Questions & Answers

A.
Lesson learned documentation
Templates

B.
Risk analysis
Rolling wave planning

C.
Preventive action
It is method of identifying and eliminating the causes of a problem, thus preventing their
reappearance. Examples of a corrective action are : Improvements to maintenance schedules
Improvements to material handling or storage
Answer option A is incorrect. Lessons learned is a documentation of the errors and how they were
resolved, not a method to prevent the errors from occurring again.
Answer option C is incorrect. Preventive action addresses any action or act in which the project
management team and the team leader provide documented direction to carry out an activity that
is meant to decrease the possibility of negative consequences related to project risk.
Answer option B is incorrect. Risk analysis examines the risk events, its probability, and its impact
on the project.
QUESTION 66

You have been assigned to a project that centers on a discipline you are only topically aware of.
While you do have years of experience as a project manager, but you have never worked with the
technology, as is in this project. During the define activities process, you rely on your project team
and two consultants to coach you and identify the type of activities the project will include. Which
tool and technique are you using in the define activities process in this scenario?
Decomposition

D.
Corrective action
Expert judgment

C.
Preventive action
It is method of identifying and eliminating the causes of a problem, thus preventing their
reappearance. Examples of a corrective action are : Improvements to maintenance schedules
Improvements to material handling or storage
Answer option A is incorrect. Lessons learned is a documentation of the errors and how they were
resolved, not a method to prevent the errors from occurring again.
Answer option C is incorrect. Preventive action addresses any action or act in which the project
management team and the team leader provide documented direction to carry out an activity that
is meant to decrease the possibility of negative consequences related to project risk.
Answer option B is incorrect. Risk analysis examines the risk events, its probability, and its impact
on the project.
QUESTION 66

You have been assigned to a project that centers on a discipline you are only topically aware of.
While you do have years of experience as a project manager, but you have never worked with the
technology, as is in this project. During the define activities process, you rely on your project team
and two consultants to coach you and identify the type of activities the project will include. Which
tool and technique are you using in the define activities process in this scenario?
Decomposition

A.
Lesson learned documentation
Templates

B.
Risk analysis
Rolling wave planning

C.
Preventive action
It is method of identifying and eliminating the causes of a problem, thus preventing their
reappearance. Examples of a corrective action are : Improvements to maintenance schedules
Improvements to material handling or storage
Answer option A is incorrect. Lessons learned is a documentation of the errors and how they were
resolved, not a method to prevent the errors from occurring again.
Answer option C is incorrect. Preventive action addresses any action or act in which the project
management team and the team leader provide documented direction to carry out an activity that
is meant to decrease the possibility of negative consequences related to project risk.
Answer option B is incorrect. Risk analysis examines the risk events, its probability, and its impact
on the project.
QUESTION 66

You have been assigned to a project that centers on a discipline you are only topically aware of.
While you do have years of experience as a project manager, but you have never worked with the
technology, as is in this project. During the define activities process, you rely on your project team
and two consultants to coach you and identify the type of activities the project will include. Which
tool and technique are you using in the define activities process in this scenario?
Decomposition

D.
Corrective action
Expert judgment

Explanation:
A corrective action is a change implemented to address a weakness identified in a management
system. Normally corrective actions are implemented in response to a customer complaint,
abnormal levels of internal nonconformity, nonconformities identified during an internal audit or
adverse or unstable trends in product and process monitoring such as would be identified by SP

When the project manager relies on consultants or the project team (or both), it is an example of
expert judgment. Expert judgment is a technique based on a set of criteria that has been acquired
in a specific knowledge area or product area. It is obtained when the project manager or project
team requires specialized knowledge that they do not possess. Expert judgment involves people
most familiar with the work of creating estimates. Preferably, the project team member who will be
doing the task should complete the estimates. Expert judgment is applied when performing
administrative closure activities, and experts should ensure the project or phase closure is
performed to the appropriate standards.
Answer option C is incorrect. This is not an example of decomposition.
Answer option B is incorrect. This is not an example of rolling wave planning.
Answer option A is incorrect. This is not an example of using a project template.