Complete this sentence: _________________________ is the process of collecting and distributing performance in

Complete this sentence:
_________________________ is the process of collecting and distributing performance
information including status reports, progress measurements, and forecasts.

PrepAway - Latest Free Exam Questions & Answers

A.
Corrective action

B.
Report performance

C.
Earned value management

D.
Monitor and control project performance

Explanation:
Report performance is a project process that collects and distributes information on the project
work.
Answer option C is incorrect. Earned value management may be used as the tool and technique
for determining project performance.
Answer option D is incorrect. Monitor and control project performance is not a project process so
this choice is not valid.
Answer option A is incorrect. Corrective action is a response to project performance to bring the
project back into alignment with expectations.