Complete this sentence:
_________________________ is the process of collecting and distributing performance
information including status reports, progress measurements, and forecasts.

A.
Corrective action
B.
Report performance
C.
Earned value management
D.
Monitor and control project performance
Explanation:
Report performance is a project process that collects and distributes information on the project
work.
Answer option C is incorrect. Earned value management may be used as the tool and technique
for determining project performance.
Answer option D is incorrect. Monitor and control project performance is not a project process so
this choice is not valid.
Answer option A is incorrect. Corrective action is a response to project performance to bring the
project back into alignment with expectations.