Steve is the project manager for the POK Project. He is working with the project customers to
determine how frequently they’d like to receive the project information. The customers would like
weekly status reports on how the project is performing. Where should Steve document this
information?
A.
Communications management plan
B.
Issues log
C.
Project schedule
D.
Schedule management plan
Explanation:
The communications management plan defines who needs what information, when the information
is needed, and the modality the information is expected in.
Answer option C is incorrect. The project schedule could include project management activities
such as schedule communication, but the communications management plan is the best answer
as this information is absolutely documented in this plan.
Answer option D is incorrect. The schedule management is not the best location for this
information.
Answer option B is incorrect. The request for customer communication is not an issue, so this
choice is not the most appropriate.