You work as a project manager for BlueWell Inc. You have to identify the specific actions to be
performed to produce the project deliverables. For this, you have to explain the three inputs for the
define activities process to your project team. Which of the following is NOT a valid input?
A.
Work Breakdown Structure
B.
Enterprise Environmental Factors
C.
Scope baseline
D.
Organizational Process Assets
Explanation:
Of all the choices, the WBS is the best choice. The entire scope baseline is needed as an input,
not just the WBS. The inputs to the Define Activities process are as follows: Scope Baseline: The
project constraints, assumptions documented, and deliverables in the project scope baseline are
considered while defining activities. Enterprise Environmental Factors: One of the factors that
affect the Define Activities process is the project management information system (PMIS).
Organizational Process Assets: The assets that can affect the Define Activities process are as
follows: 1.The existing proper and unofficial scheduling strategies, procedures, and related policies
that are measured in developing the activity definitions 2.The lessons-learned knowledge base
containing the past information about activity lists used by similar earlier projects