what project document must be updated to reflect this change to the approach?

Holly is the project manager of her project. She has chosen to crash the project due to time
constraints that have been imposed on her project. When Holly crashes the project what project
document must be updated to reflect this change to the approach?

PrepAway - Latest Free Exam Questions & Answers

A.
Develop schedule process

B.
Risk register

C.
Project risk management plan

D.
Activity attributes

Explanation:
When Holly adds resources to the project, as in this instance, she will need to update the activity
attributes to reflect the new labor. Activity attributes are an output of the Define Activity process.
These attributes refer to the multiple components that frame up an activity. The components for
each activity during the early stages of the project are the Activity ID, WBS ID, and Activity name.
At the later stages, the activity attributes include Activity codes, Predecessor activity, activity
description, logical relationship, successor activity, leads and lags, imposed dates, and constraints
and assumptions. Activity attributes are used for schedule development and for ordering,
selecting, and sorting the planned schedule activities in a number of ways within reports. In project
document updates, activity attributes are updated to include any revised resource requirements
and other revision generated by the develop schedule process.

2 Comments on “what project document must be updated to reflect this change to the approach?