What is one of the first steps in developing a business continuity plan?

A.
Identify backup solution.
B.
Decide whether the company needs to perform a walk-through, parallel, or simulation test.
C.
Perform a business impact analysis.
D.
Develop a business resumption plan.
Explanation:
C: A business impact analysis includes identifying critical systems and functions of a company and interviewing representatives from each department. Once managements support is solidified, a business impact analysis needs to be performed to identify the threats the company faces and the potential costs of these threats.
A business impact analysis includes identifying critical systems and functions of a company and interviewing representatives from each department. Once managements support is solidified, a business impact analysis needs to be performed to identify the threats the company faces and the potential costs of these threats.