PrepAway - Latest Free Exam Questions & Answers

The purpose of initiating emergency actions right after a disaster takes place is to prevent loss of life, att

The purpose of initiating emergency actions right after a disaster takes place is to prevent loss of life, attend to injuries, and __________.

PrepAway - Latest Free Exam Questions & Answers

A.
Secure the area to ensure that no looting or fraud takes place

B.
Mitigate further damage

C.
Protect evidence and clues

D.
Investigate the extent of the damages

Explanation:
The main goal of disaster recovery and business continuity plans is to
mitigate all risks that could be experienced by a company. Emergency procedures need
to be carried out first to protect human life. Then other procedures need to be
executed to reduce the damage from further threats.