What should be moved in first?

Gizmos and Gadgets has restored its original facility after a disaster. What should be moved in first?

PrepAway - Latest Free Exam Questions & Answers

A.
Management

B.
Most critical systems

C.
Most critical functions

D.
Least critical functions

Explanation:
D: After the primary site has been repaired, the least critical components are moved in first. This ensures that the primary site is really ready to resume processing. By doing this,
you can validate that environmental controls, power, and communication links are working properly. It can also avoid putting the company into another disaster. If the less critical
functions survive, then the more critical components of the company can be moved over.
A is incorrect because personnel should not be moved into the facility until it is determined that the environment is safe, everything is in good working order, and all necessary
equipment and supplies are present. Least critical functions should be moved back first, so if there are issues in network configurations or connectivity, or important steps were not
carried out, the critical operations of the company are not negatively affected.
B is incorrect because the most critical systems should not be resumed in the new environment until it has been properly tested. You do not want to go through the trouble of moving
the most critical systems and operations from a safe and stable site, only to return them to a main site that is untested. When you move less critical departments over first, they act as
the canary. If they survive, then move on to critical systems.
C is incorrect because the most critical functions should not be moved over before less critical functions, which serve to test the stability and safety of the site. If the site proves to
need further preparation, then no harm is done to the critical functions.

One Comment on “What should be moved in first?

  1. joe says:

    After the primary site has been repaired, the least critical components are moved in first. This ensures that the primary site is really ready to resume processing. By doing this, you can validate that environmental controls, power, and communication links are working properly. It can also avoid putting the company into another disaster. If the less critical functions survive, then the more critical components of the company can be moved over.