Which of the following actions is least important when quantifying risks associated with a potential disaster?

Which of the following actions is least important when quantifying risks associated with a potential disaster?

PrepAway - Latest Free Exam Questions & Answers

A.
Gathering information from agencies that report the probability of certain natural disasters taking place in that area

B.
Identifying the company�s key functions and business requirements

C.
Identifying critical systems that support the company�s operations

D.
Estimating the potential loss and impact the company would face based on how long the outage lasted

Explanation:
A: The question asked you about quantifying the risks, which means to calculate the potential business impact of specific disasters. The core components of a business impact analysis are
Identifying the companys key functions and business requirements
Identifying critical systems that support the companys operations
Estimating the potential loss and impact the company would face based on
how long the outage lasted
Gathering information from agencies that report the probability of certain
natural disasters taking place in that area is an important piece in determining
the probability of these threats, but it is considered least necessary when
quantifying the potential damage that could be experienced.