Project management for software development has several phases. Which of thefollowing lists these phases in the correct order?

PrepAway - Latest Free Exam Questions & Answers

A.
Project initiation, system design specifications, functional design analysis andplanning, software development, installation/implementation,operational/maintenance, disposal

B.
Project initiation, functional design analysis and planning, system design specifications, software development, installation/implementation,operational/maintenance, disposal

C.
Project initiation, functional design analysis and planning, software development, system design specifications, installation/implementation,operational/maintenance, disposal

D.
Project initiation, system design specifications, functional design analysis and planning, software development, operational/maintenance,installation/implementation, disposal

Explanation:
Software development project management should take place in thefollowing phases;

1. Project initiation
2. Functional design analysis and planning
3. System design specifications
4. Software development
5. Installation/implementation
6. Operational/maintenance
7. Disposal