_______________ includes activities to test and validate system capability and functionality and outlines actions that can be taken to return the system to normal operating condition and prepare the system against future outages.

PrepAway - Latest Free Exam Questions & Answers

A.
Activation

B.
Recovery

C.
Reconstitution

D.
Validation

Explanation:
The Activation/Notification Phase describes the process of activating
the plan based on outage impacts and notifying recovery personnel. The Recovery
Phase details a suggested course of action for recovery teams to restore system
operations at an alternate site or using contingency capabilities. The final phase,
Reconstitution, includes activities to test and validate system capability and
functionality and outlines actions that can be taken to return the system to normal
operating condition and prepare the system against future outages.