Which of the following statements is false?

Which of the following statements is false?

PrepAway - Latest Free Exam Questions & Answers

A.
A disaster recovery team�s primary task is to restore critical business functions at the alternate backup processing site.

B.
A disaster salvage team�s task is to ensure that the primary site returns to normal processing conditions.

C.
The disaster recovery plan should include how the company will return from the alternate site to the primary site.

D.
When returning to the primary site, the most critical applications should be brought back first.

Explanation:
When the primary site is ready to receive operations again, less
critical systems should be brought back first to ensure that everything is running
smoothly before returning critical systems, which are already operating normally at
the recovery site.