which process is Problem Management likely to share categorization and impact coding systems?

With which process is Problem Management likely to share categorization and impact coding
systems?

PrepAway - Latest Free Exam Questions & Answers

A.
Incident Management

B.
Service Asset and Configuration Management

C.
Capacity Management

D.
IT Service Continuity

One Comment on “which process is Problem Management likely to share categorization and impact coding systems?

  1. Michael McNeil says:

    Although Incident and Problem Management are separate
    processes, they are closely related and will typically use
    the same tools, and may use similar categorization, impact
    and priority coding systems. This will ensure effective
    communication when dealing with related Incidents and
    Problems.