1. Progress
2. Effectiveness
3. Efficiency
4. ?

PrepAway - Latest Free Exam Questions & Answers

A.
Cost

B.
Conformance

C.
Compliance

D.
Capacity

One Comment on “Which of the four metrics is missing from the list below?

  1. Michael McNeil says:

    The process measurements selected need to be
    appropriate for the capability and maturity of the
    processes being measured. Immature processes are not
    capable of supporting sophisticated measurements,
    metrics and measurement methods. There are four types
    of metrics that can be used to measure the capability and
    performance of processes:
    ■ Progress: milestones and deliverables in the capability
    of the process
    ■ Compliance: compliance of the process to governance
    requirements, regulatory requirements and compliance
    of people to the use of the process.
    ■ Effectiveness: the accuracy and correctness of the
    process and its ability to deliver the ‘right result’
    ■ Efficiency: the productivity of the process, its speed,
    throughput and resource utilization.