Which of the following would NOT be a task carried out by the Request Fulfillment process?

Which of the following would NOT be a task carried out by the Request Fulfillment process?

PrepAway - Latest Free Exam Questions & Answers

A.
The sourcing and delivering of the components of requested standard services (e.g. licenses
and software media)

B.
Provision of a channel for users to request and receive standard services for which a pre-defined approval and qualification process exists

C.
Provision of information used to compare actual performance against design standards

D.
Provision of information to users and customers about the availability of services and the
procedure for obtaining them