Which of the following provides resources to resolve operational and support issues during
Release and Deployment?

A.
Early Life Support
B.
Service Test Manager
C.
Evaluation
D.
Release Packaging and Build Manager
You must be logged in to post a comment.
10.5.4 Stage 4 – Operate the service
In our scenario we have now deployed the new service
and have accepted it into live operation. But the work
from Strategy, Design and Transition is not done.
Early life support is a critical part of ensuring that what we
have planned, built, tested and installed is producing the
predicted results and meeting the business outcomes we
started with.
Beyond early life support, the service becomes ‘business as
usual’ and is continuously monitored and controlled,
becoming part of the overall service value to the business
customer.