Who is responsibility for making sure that a message in the project team is understood
A.
Project Manager
B.
Sender
C.
Project coordinator
D.
Sponsor
Explanation:
The sender has to make sure that the receiver acknowledges the receipt and message is understood, and the receiver needs to ensure that the sender received the acknowledgement.
Correct answer is B
0
0
By adding project team in there, it throws the answer off.