PrepAway - Latest Free Exam Questions & Answers

This is an example of which of the following?

You are the project manager for the software Project. This project must be completed within one year. This is an example of which of the following?

PrepAway - Latest Free Exam Questions & Answers

A.
Schedule

B.
Assumption

C.
Constraint

D.
Planning process

Explanation:
A project that must be completed by a deadline is dealing with time constraints. A is incorrect since the condition does not offer a schedule. B is incorrect because the condition is not an assumption. D is also incorrect because this is not a planning process.

One Comment on “This is an example of which of the following?


Leave a Reply