This is an example of _________.

You are the project manager for a Software Development projects. You are creating a project schedule network diagram for the code development component of the project. This is an example of _________.

PrepAway - Latest Free Exam Questions & Answers

A.
Fragment Network

B.
Precedence Diagramming Method [PDM]

C.
Activity On Node [AON]

D.
Arrow Diagramming Method [ADM]

Explanation:
It is not clear what Sequence Activities technique you are using. However, you are developing a schedule network diagram for only part of the project.