Assumptions in the project plan should be _________.

Assumptions in the project plan should be _________.

PrepAway - Latest Free Exam Questions & Answers

A.
Written down

B.
Understandable

C.
Not understandable

D.
No need to write

Explanation:
Assumptions that are not written down are the most dangerous.