The project baseline is _______.
A.
Original plans plus the approved changes
B.
Important in the project initiation phase
C.
Initial estimates for tasks and resource utilization
D.
Original plans and the approved major changes
Explanation:
The project baseline: original plans plus the approved changes.
I agree with the answer. A