The project baseline is _______.

The project baseline is _______.

PrepAway - Latest Free Exam Questions & Answers

A.
Original plans plus the approved changes

B.
Important in the project initiation phase

C.
Initial estimates for tasks and resource utilization

D.
Original plans and the approved major changes

Explanation:
The project baseline: original plans plus the approved changes.