PrepAway - Latest Free Exam Questions & Answers

Resource reallocation from non critical to critical activities is an example of which of the following Project

Resource reallocation from non critical to critical activities is an example of which of the following Project Scheduling technique:

PrepAway - Latest Free Exam Questions & Answers

A.
Resource Leveling

B.
Schedule Compression

C.
Critical Path Method

D.
What if Analysis

Explanation:
Resource Leveling :Allocate scare resources to critical path activities first .

One Comment on “Resource reallocation from non critical to critical activities is an example of which of the following Project


Leave a Reply