All of the following are tools and techniques that may be used during this process:

During the Develop Schedule process, a Project Manager may have to go through several iterations of the schedule before establishing the schedule baseline. All of the following are tools and techniques that may be used during this process:

PrepAway - Latest Free Exam Questions & Answers

A.
Critical Path Method, GERT, Resource Requirements

B.
Resource Levelling Heuristics, Mathematical Analysis, Calendar!

C.
Duration compression, Resource Leveling Heuristics, PERT

D.
GERT, PERT, Leads and Lags