Which document is best suited for tracking the assignment of all resources to specific tasks in a project?
A.
RACI mAl,x
B.
sow
C.
Staffing management plan
D.
CPI
Explanation:
The RACI matrix lists responsibilities of all resources. The staffing management plan only lists types of resources and timing.
I choose A