Which of the following is NOT considered as strategy for negative risk ?

Which of the following is NOT considered as strategy for negative risk ?

PrepAway - Latest Free Exam Questions & Answers

A.
Avoid

B.
Transfer

C.
Accept

D.
ExPlot

Explanation:
D is the correct answer. Exploit is considered as strategy for positive risk.Strategies for negative risks are Avoid ,Transfer,Mitigate and Accept.