Which of the following are examples of indirect costs?
A. Salaries of corporate executives
B. Salaries of full-time project staff
C. Overhead costs
D. Both a and c
Explanation: Salaries of full-time project staff included in direct cost.
3 Comments on “Which of the following are examples of indirect costs?”
mr_tienvusays:
I agree with the answer. D
0
0
mesays:
A collection of logically related project activities that culminates in the completion of one or more deliverables is called a:
a. project phase
b. product validation
c. phase gate
d. project plan
The answer is: a
0
0
mesays:
Why is the Cost Performance Index (CPI) considered the most critical EVM metric?
a. It measures how efficiently the project team is using its time.
b. It measures the cost efficiency for the budgeted resources.
c. It is a measure of schedule performance on a project.
d. It is a measure of cost performance on a project.
I agree with the answer. D
0
0
A collection of logically related project activities that culminates in the completion of one or more deliverables is called a:
a. project phase
b. product validation
c. phase gate
d. project plan
The answer is: a
0
0
Why is the Cost Performance Index (CPI) considered the most critical EVM metric?
a. It measures how efficiently the project team is using its time.
b. It measures the cost efficiency for the budgeted resources.
c. It is a measure of schedule performance on a project.
d. It is a measure of cost performance on a project.
The answer is: b
0
0