The major project scope management process includes:
A. Change order control
B. Initiation
C. Program evaluation
D. Scope statement
Explanation: Initiation included in major project scope management processes
2 Comments on “The major project scope management process includes:”
seenagapesays:
Correct answer is B
0
0
PMIguysays:
This is a very poorly worded question. Even so, there are no processes in the Initiating Process Group under the Scope Management Knowledge Area. Therefore, the answer is definitely NOT A. Since the Scope Statement is one of the primary outputs of this process, the answer should be D.
Correct answer is B
0
0
This is a very poorly worded question. Even so, there are no processes in the Initiating Process Group under the Scope Management Knowledge Area. Therefore, the answer is definitely NOT A. Since the Scope Statement is one of the primary outputs of this process, the answer should be D.
Correct Answer is D.