Collect Requirements process starts in Project Planning Phase and uses the outputs of the __________.

Collect Requirements process starts in Project Planning Phase and uses the outputs of the __________.

PrepAway - Latest Free Exam Questions & Answers

A.
Initiation Process

B.
Project closer Process

C.
Estimation Process

D.
Closing process

Explanation:
Collect Requirements process starts in “Project Planning Phase” and uses the outputs of the Initiation Process.