What effect will this have on the project?

During the execution phase, a resource is added to the project team. What effect will this have on the project?

PrepAway - Latest Free Exam Questions & Answers

A.
The effect cannot be determined

B.
The project duration will be shortened

C.
A scope change will be required

D.
The quality of the project will be increased