A.
Project statement of work, Contract, Business case and organizational process assets

B.
Project SOW, project selection methods, and enterprise environmental factors

C.
Contract, project selection methods, enterprise environmental factors, and organizational process assets

D.
Contract, project SOW, enterprise environmental factors, and organizational process assets

Explanation:
Inputs to the Develop Project Charter process are Project statement of work, Contract, Business case and organizational process assets.