PrepAway - Latest Free Exam Questions & Answers

If a project with a CPI of 1.2, what you tell?

If a project with a CPI of 1.2, what you tell?

PrepAway - Latest Free Exam Questions & Answers

A.
The project is consuming fewer resources than anticipated

B.
The project is using fewer resources than anticipated.

C.
The project is falling behind.

D.
The project is running ahead of schedule.

Explanation:
If your cost performance index is above 1.0, it indicates that you have costs that are less then estimated; so doing good . Option A is BEST fit for this CPI = EV/AC (Earned value/ Actual cost

4 Comments on “If a project with a CPI of 1.2, what you tell?


Leave a Reply