A graphic display of resource usage hours is called a/an_________________.

A graphic display of resource usage hours is called a/an_________________.

PrepAway - Latest Free Exam Questions & Answers

A.
Organizational chart

B.
Responsibility matrix

C.
WBS

D.
Histogram

Explanation:
histogram that is useful in determining how much time is expected from the various team members and or functions.