You are working with an organization and you found that one stakeholder not disclosing all of the costs involved with an upcoming project. Rather, this CAPM is constructing a WBS that does not include all the tasks necessary to get the project done. What you should do?

PrepAway - Latest Free Exam Questions & Answers

A.
Talk to the CAPM about the WBS to see if you can rework it to reflect actual costs of the project

B.
Confront the other project manager immediately

C.
Mail to PMI headquarters

D.
Ignore it

Explanation:
You can talk to the CAPM about the WBS changes. If he or she refuses to change the WBS, you have a responsibility to go to stakeholders and voice your concerns.