Based on the PMBOK, who is ultimately responsible for the project quality?

Based on the PMBOK, who is ultimately responsible for the project quality?

PrepAway - Latest Free Exam Questions & Answers

A.
Project team

B.
Project manager

C.
QA manager

D.
Validation engineer

Explanation:
Project manager IS ultimately responsible for the project quality