PrepAway - Latest Free Exam Questions & Answers

What is the BAC?

You are the project manager of the MKTG Project. The project has a budget of $200,000 and is expected to last 2 years. The project is now 20 percent complete and is on schedule. What is the BAC?

PrepAway - Latest Free Exam Questions & Answers

A.
$-00,000

B.
$200,00

C.
$50,000

D.
None of the above

Explanation:
The BAC is the budget at completion (Total budgeted cost), which is $200,000.