You are the project manager for Tech Days Seminar Homes. Your new project assignment is to head the Days Seminar Home opening in Mountainview, CA. You are estimating the duration of the project plan activities, devising the project schedule, and monitoring and controlling deviations from the schedule. Which of the Project Management Knowledge Areas are you working in?

PrepAway - Latest Free Exam Questions & Answers

A.
Project Scope Management

B.
Project Quality Management

C.
Project Integration Management

D.
Project Time Management

Explanation:
Project Time Management involves the following processes: Define Activities, Activity Sequencing, Estimate Activity Durations, Develop Schedule, and Control Schedule.