What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack?

What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack?

PrepAway - Latest Free Exam Questions & Answers

A.
Lots of free float

B.
Idle resources

C.
Negative float

D.
Positive float